Kickoff of operation to move Hydra into campus#
The start of the operation to move the Hydra cluster to VUB Etterbeek campus is upon us. Hydra will be closed to access from Monday, April 11th at 00:00 (CEST). The move is planned to last 1 week. We will continue to be reachable at hpc@vub.be and we will communicate the progress of the move on this post.
If you are not yet familiar with the implications of this move, you can find all the information in the announcement page: Hydra moves to VUB Etterbeek campus
During the week of the move, users can still contact us at VUB-HPC Support but user support will be limited:
Login to Hydra and other VSC sites (except Tier-1 Hortense) will be closed
Requests requiring access to the HPC cluster (e.g. software installations, data transfers) will only be possible once all systems are back online
Creation of new VSC user accounts and VOs will be paused until the new storage is fully integrated with the VSC account page
Timeline of events#
The timeline below shows the main goalposts during this operation and it will be updated regularly. We will also notify of any changes on the planned schedule.
Date |
Time |
Action |
Status |
---|---|---|---|
11/04 |
00:00 |
Access of VUB users to all VSC clusters closed |
✓ Completed |
11/04 |
08:00 |
Final data sync to new storage |
✓ Completed |
12/04 |
08:00 |
Move of hardware to Etterbeek campus |
✓ Completed |
19/04 |
17:00 |
Login to non-VUB VSC clusters re-established |
↩ Updated ETA ✓ Completed |
19/04 |
17:00 |
Login to Hydra re-established |
↩ Updated ETA ✓ Completed |
25/04 |
18:00 |
Creation of new VSC accounts and VOs re-established |
✓ Completed |
Updated on 19/04/2022
13:00 We are happy to announce that all issues have been solved. Not only is the network working, but we also completed the integration of the new storage. We are now wrapping up the last bits before we open the cluster to the public. Final time for the re-opening is today at 17:00.
Updated on 15/04/2022
20:00 We deeply regret to announce that the re-opening of Hydra has to be postponed. Outstanding issues with the network connection of some critical systems (e.g. the login nodes) pushed us to cancel the re-establishment of services.
On the positive side, today we solved the main hardware issue encountered during the move and we recovered the non-operational InfiniBand network switch. As of this writing all hardware parts/nodes in Hydra are functional. Hence, we will be able to re-open the cluster to our users (even if partially) fairly quickly once all core systems have full access to the networks of Hydra.
Our apologies for the inconvenience.
Updated on 14/04/2022
20:00 Cabling of the all nodes is almost complete. We already powered up and tested the core systems in Hydra and no major problems have occurred. We currently have 2 active issues that are causing changes in our planning:
Network access to the new storage is limited
One InfiniBand network switch is non-operational
Tomorrow we plan to do the first global stress-test of the complete cluster. If there are no critical failures, Hydra will be brought online as planned. However, due to the aforementioned issues, access to other VSC sites will only be possible when Hydra is online. If these issues persist, the re-establishement of services might be partial and the kickoff of the new storage postponed to a later date.
Updated on 13/04/2022
19:00 All hardware parts of Hydra are already placed in their new
location in the VUB data center. User data was successfully transferred to
the new storage and $VSC_HOME
and $VSC_DATA
are in a good state. We
are still working on re-opening access to clusters in other VSC sites, this
requires making the storage accessible from external VSC sites which is in
progress.
Updated on 13/04/2022
9:00 All hardware parts of Hydra have already arrived at VUB Etterbeek campus.
Installation of the nodes is currently ongoing. The focus today will be on
bringing the new storage for $VSC_HOME
and $VSC_DATA
online. This will
allow all our users to use any of the other VSC clusters.
Updated on 12/04/2022
09:00 All necessary preparations to move the hardware of the HPC cluster have been carried out succesfully and on schedule. Today Hydra will be transported piece by piece into its new location in VUB Etterbeek campus.